QUESTION 1
Your program has 121 stakeholders that you’ll need to communicate with. Your communications management plan defines how the communication
should happen, what should be communicated, and the expected modality of the communications. You’ll also need which one of the following as an
input to the information distribution process in your program?
A. Change requests
B. Earned value management results
C. Stakeholder analysis plan
D. Performance reports

Correct Answer: C

QUESTION 2
What is the formula to determine earned value (EV) for a program?
A. Percent complete times percent remaining in the program
B. Percent completes time the program cost estimate
C. Percent complete times the program budget at completion
D. Percent complete times the program cost of labor and materials

Correct Answer: C

QUESTION 3
Olive is the program manager for her organization. She has created a request for proposal for a large portion of her program. In this work to be procured
she has set several requirements for the vendors to participate. The chief among these requirements is a vendor must have at least four licensed
electricians in his team. This requirement for four licensed electricians is an example of which one of the following terms?
A. Screening system
B. Scoring model

C. Vendor analysis requirements
D. Evaluation criteria

Correct Answer: A

QUESTION 4
You are the program manager for your organization. Management has asked you to create a document that will capture the stakeholders concerns,
perceived threats, and specific objectives about the program and its projects. What document is management asking you to create in this instance?
A. Requirements document
B. Project charter
C. Business case
D. Scope statement

Correct Answer: D

QUESTION 5
You are the program manager of the NHQ Program. You are working with your program team to ensure that the work in the program is done accurately
and according to scope. You are also reviewing the team inspection process that will need to be done to ensure that the work is being done according to
the scope. If the work is found to be defective it will need to be corrected before the program customers can inspect the work. What process are you
completing to ensure that the work is done accordingly to scope?
A. Quality control
B. Scope verification
C. Quality assurance
D. Planning

Correct Answer: C