PMP Project Management Professional v6
QUESTION 1
An element of the project scope statement is:
A. Acceptance criteria.
B. A stakeholder list.
C. A summary budget,
D. High-level risks.
Correct Answer: A
QUESTION 2
Which document describes the necessary information to determine if a project is worth the required investment?
A. Cost baseline
B. Service level agreement
C. Memorandum of understanding
D. Business case
Correct Answer: D
QUESTION 3
Which input to the Plan Risk Management process provides information on high-level risks?
A. Project charter
B. Enterprise environmental factors
C. Stakeholder register
D. Organizational process assets
Correct Answer: A
QUESTION 4
Which item is an example of a personnel assessment?
A. Resource calendar
B. Tight matrix
C. Team-building activity
D. Focus group
Correct Answer: D
QUESTION 5
Which input to the Manage Stakeholder Engagement process provides guidance on how stakeholders can best be involved in a project?
A. Feedback analysis
B. Stakeholder analysis
C. Communication management plan
D. Stakeholder management plan
Correct Answer: D